- Saudi Aramco shut its 400,000-barrel-per-day Jazan refinery on July 27 after a Houthi attack damaged the facility, according to an IIR note seen by Reuters.
- The attack on the Jazan refinery occurred on July 25, causing damage to its Integrated Gasification Combined Cycle complex and tank farm area.
- Repairs are tentatively expected to be completed by August 15, according to the consultancy note.
- The Jazan refinery removes 400,000 bpd of capacity, which is significant given the current tight fuel market.
- Gasoline, diesel, and jet fuel supplies were already tight, with inventories thin and refining margins having surged prior to the attack.
Saudi Aramco has temporarily closed its Jazan refinery, which processes 400,000 barrels per day, following a Houthi attack on July 27 that caused significant damage. The attack impacted the refinery's Integrated Gasification Combined Cycle complex and tank farm area, leading to a shutdown that could last until August 15 for repairs.1234567
The Houthi military spokesman Yahya Saree claimed responsibility for the attack, stating that the group also targeted Aramco facilities in Yanbu. The incident has raised concerns in an already tight fuel market, where gasoline, diesel, and jet fuel supplies are limited, and refining margins have surged.89
While a shutdown of less than three weeks may not seem catastrophic, the loss of 400,000 bpd from the Jazan refinery exacerbates existing supply issues. Consultancy IIR noted that the refinery's damage could have broader implications for fuel availability in the region, as inventories were already thin prior to the attack.

Video verified by Reuters showed a large plume of smoke rising from the refinery following the attack, highlighting the severity of the damage sustained during the incident.
As the situation develops, the focus remains on the timeline for repairs and the potential impact on fuel prices and availability in the coming weeks.
“The Jazan refinery, which processes 400,000 barrels per day, sustained significant damage to its Integrated Gasification Combined Cycle complex and tank farm area. With gasoline, diesel, and jet fuel supplies already tight, the shutdown could exacerbate existing fuel shortages in the region.”