- Johor Bahru High Court ordered developer R&F Development Sdn Bhd to pay RM10.56 million (approximately US$2.58 million) to the owners of 84 apartments at the R&F Princess Cove residential complex for delays in handing over units and completing common facilities.
- The court found that R&F had breached the sale and purchase agreements by splitting the original first phase of the project into two separate phases.
- The court dismissed claims concerning 39 units, ordering their owners to pay R&F legal costs of 10,000 ringgit for each apartment.
- R&F Development intends to appeal the ruling, as do the buyers whose claims were dismissed.
- Buyers of apartments in three residential blocks received their keys on October 25, 2017, but the entire original first phase was completed only in November 2018.
- The lawsuit was filed in 2019 with 145 named plaintiffs and initially resulted in a court ruling in buyers' favor in 2021 without a full trial.
- A 10-day trial concluded in 2024 before the latest ruling was delivered on September 10, 2026.
- The court ruled that November 2018 should be used as the date for calculating compensation for the delay, rather than October 2017.
The Johor Bahru High Court has mandated R&F Development Sdn Bhd to compensate 84 condominium owners, including Singaporeans, a total of RM10.56 million (US$2.58 million) for delays in the R&F Princess Cove project. The court found that R&F breached sale agreements by splitting the original first phase into two separate phases, Phase 1A and Phase 1B.12
Buyers received keys to their units on October 25, 2017, but the entire original phase was not completed until November 2018. The court ruled that this date should be used for calculating compensation, which amounted to 10% per year of each unit's value for delayed handover and 10% per year of one-fifth of the apartment price for unfinished common facilities.912
Each of the 84 owners was awarded between RM34,000 to RM196,000 for delays in receiving their apartments and RM6,900 to RM39,000 for the incomplete common facilities. Additionally, R&F was ordered to refund maintenance charges and other fees collected before November 8, 2018.
The court dismissed claims from another 39 apartments, ordering their owners to pay RM10,000 (US$2,454) in legal costs each. R&F's representative, Josiah Tea, stated the developer intends to appeal the ruling, while the buyers' lawyer, N.G. Vinod, indicated that dismissed claimants also plan to appeal.78
This ruling underscores the necessity for developers to adhere to contractual obligations, a critical lesson for future property buyers in Johor Bahru.
“The court awarded owners RM34,000 to RM196,000 per unit for late delivery and RM6,900 to RM39,000 for unfinished shared facilities, plus refunds of maintenance fees. A separate 2023 lawsuit over delayed strata titles, involving 167 owners, won only legal costs, not damages, as titles were later issued.”