Adani Energy to expand Maharashtra network with 3,000 MVA substations in $194m project

Adani Energy Solutions Limited has secured a Rs16.6bn ($194.2m) interstate transmission project to boost renewable energy evacuation in Maharashtra. The project will add 3,000 MVA substations and expand AESL's network to 26,696 circuit kilometres, significantly enhancing power transmission capacity to Mumbai and surrounding areas.

Sources:
1
Updated 59m ago
Tab background
Sources: 1
India’s Adani Energy Solutions Limited (AESL) has secured a significant Rs16.6 billion ($194.2 million) interstate transmission project in Maharashtra, aimed at bolstering the state’s renewable energy infrastructure.

The project focuses on installing 3,000 megavolt-amperes (MVA) of substation capacity to facilitate the evacuation of 1.5 gigawatts (GW) of renewable energy from upcoming hydro pumped storage projects in Raigad district. This energy will be transmitted to Mumbai and surrounding areas, enhancing grid stability and supporting India’s clean energy goals.

“The project will expand AESL’s transmission network to 26,696 circuit kilometres and 93,236 MVA of transformation capacity,” highlighting the company’s growing footprint in the power transmission sector.

AESL won the interstate transmission system (ISTS) project through a tariff-based competitive bidding (TBCB) process, coordinated by REC Power Development and Consultancy (RECPDCL). This competitive process underscores the project’s strategic importance and AESL’s capability in executing large-scale transmission infrastructure.

The expansion aligns with India’s broader push to integrate renewable energy sources into the grid, particularly hydro pumped storage, which plays a critical role in energy storage and grid balancing.

Key stats:
- Project value: Rs16.6 billion ($194.2 million)
- Substation capacity: 3,000 MVA
- Renewable energy evacuation: 1.5 GW
- Transmission network expansion: 26,696 circuit km
- Transformation capacity post-project: 93,236 MVA

This project marks a major step in Maharashtra’s energy infrastructure development, supporting sustainable energy transmission and reinforcing AESL’s position as a leading private transmission and distribution entity in India.
Sources: 1
Adani Energy Solutions Limited has won a $194.2 million interstate transmission project in Maharashtra, India, to install 3,000 MVA substations. The project will support 1.5GW renewable energy evacuation from hydro pumped storage in Raigad, expanding AESL’s network to 26,696 circuit km and 93,236 MVA capacity.
Section 1 background
Key Facts
  • Adani Energy Solutions Limited (AESL) has secured a Rs16.6bn ($194.2m) interstate transmission project in Maharashtra, India.1
  • AESL won the interstate transmission system (ISTS) project through the tariff-based competitive bidding (TBCB) process, coordinated by REC Power Development and Consultancy (RECPDCL).1
  • The project is designed to evacuate 1.5GW of renewable energy from upcoming hydro pumped storage projects in Raigad, Maharashtra, to Mumbai and neighbouring regions.1
  • The project includes installation of 3,000 megavolt-amperes (MVA) of substations capacity and related transmission infrastructure.1
  • Upon completion, AESL’s transmission network will expand to 26,696 circuit kilometres and 93,236 MVA of transformation capacity.1
Key Stats at a Glance
Value of interstate transmission project secured by AESL
$194.2m
Renewable energy evacuation capacity
1.5GW
1
Substations capacity to be installed
3,000MVA
1
AESL transmission network length after project completion
26,696circuit kilometres
1
AESL transformation capacity after project completion
93,236MVA
1